We would like to keep the membership updated on the resurfacing process that started on Tue, June 22nd:

 

  • Power washing of the courts has completed
  • Court patching has started as of Thu and continues today (Fri)
  • The posts have been removed and new posts will be installed by the end of the week
  • What is left to be done:
    • Grinding the patched spots
    • Adding several layers of new material and painting the courts (including hitting wall area) and lines
  • The contracting company needs at least 3-4 more sunny and dry days to complete the project

 

We will keep you posted on the progress and expected re-opening day. You can monitor the progress by logging in and looking at the court camera pictures. We apologize for the inconvenience but rest assure that courts will be in great condition (brand new) when Club reopens. Stay tuned.